Home > Legal Discussion Forums > Labour / Employee Related Laws

Bocw form iv - complection of project

koshish1971 - Member Since: Dec 2010
Subject - Bocw form iv - complection of project
Dear All,

Can any body kindly provide form IV after complection of civil work under BOCW Act.

Regards,
jpratap - Member Since: Oct 2008
Subject - Re: Bocw form iv - complection of project
Form IV is attached. Commencement of work and completion of work are to be filled in the same form but at different times i.e. Before starting work, it is to be used as a form for commencement of work and when the work is finished, it is to be used as the completion of work.

Attached Files
File Type: pdf Form IV of BOCW Rules.pdf (5.7 KB, 65 views)
rajjukumar - Member Since: Jan 2011
Subject - Re: Bocw form iv - complection of project
Bocw act 1996 is applicable on the site , under this there is provision of cess to pay to secratary welfare board which is 1% of the cost of the project.in this case cost of the land is not counted for calculation of cess.
this amount goes to different welfare work of workers engaged in construction work.
raj
kapildevsingh - Member Since: Feb 2012
Subject - Re: Bocw form iv - complection of project
Quote:
Originally Posted by rajjukumar View Post
Bocw act 1996 is applicable on the site , under this there is provision of cess to pay to secratary welfare board which is 1% of the cost of the project.in this case cost of the land is not counted for calculation of cess.
this amount goes to different welfare work of workers engaged in construction work.
raj


Dear Rajju,

As per the provision of BOCW welfare cess Act, BOCW Cess is 1-2% of construction cost not of project cost and it excludes following:

1) Cost of Land
2) Cost of Compensation paid under Employee Compensation Act (earlier known as workmen compensation)

Normally state govt. are asking for 1% cess on construction cost
jpratap - Member Since: Oct 2008
Subject - Re: Bocw form iv - complection of project
Dear Kapil and Rajju,

The exact position with regard to charging of cess by States is on the basis of notification of Central Government which is 1% of the cost of construction. This software does not accept a bigger file. Kindly ask the same from me on my email address at

 


Topic Categories >> 1 ° bocw act ° construction work ° employee compensation act ° form iv ° workmen compensation °

More replies may exists. Please Login To View All Replies (Forgot Password?) (Enroll & Register)
User Name: Password:

CiteLegal is a community KnowledgeBase available to everyone at no cost.


Sponsor Cite.CO - Contact Us - CiteLegal Index - Privacy Statement - Top - RSS    

Privacy Policy | Disclaimer | Terms Of Service